•
Pre-application
conference with city staff, departments 2-4 weeks prior to submittal
•
Application Submittal
•
Site plans, elevations, landscaping, conceptual grading
•
Photographs of site and surrounding properties
•
Project Descriptions
•
Mailing labels for properties within 600 feet of site
•
Completed application
•
Completed environmental application
•
Application fees
Upon determination of completeness, the project is routed to departments for
review and conditions.
•
City departmental
review- Most cities hold a formal review meeting with representatives from the
development departments to discuss the project and review the conditions.
The applicant may or may not be invited.
•
Department Review
Committee- The public hearing must be noticed to surrounding property owners.
The applicant is invited and permitted to address the Commission. The
public can also address the Commission regarding their support or opposition to
the project. After the public hearing is closed, the Planning Commission
will either approve or deny the application. (The can also continue it to
another meeting if they feel additional information or research needs to be
done.)
•
Planning Commission
Public Hearing
•
City Council
Some cities require a CUP to be approved by the City
Council either as a Consent Calendar item, or a full public hearing review.
C. Environmental Review
The environmental review typically occurs concurrently
with the CUP process and is approved by the same body which issues final approval of the
CUP. It is this review which determines the adequacy of the technical studies and
identifies appropriate mitigation to potential impacts (e.g. a traffic signal at an
intersection to make the traffic work).
D. Appeal Period
Upon final decision, there is usually a specified appeal
period wherein an appeal can be filed against the decision. The appeal period can be
anywhere from 10 to 30 days. (10 or 15 is typical).
Pre-Construction Phase
The Intelisyn management process emphasizes the
importance of the project pre-construction phase. Proper planning and execution of
pre-construction tasks will minimize the potential for unexpected costs and schedule
delays during construction. During pre-construction, Intelisyn will establish the proper
foundation for project. At the inception of the project, schedule and budget goals will be
established and the responsibilities of each team member will be clearly defined. Systems
and procedures to ensure maximum reimbursement from FEMA and insurance companies will be
implemented if applicable. As the design concept progresses, the building configuration is
closely monitored. All elements of the design are scrutinized with particular attention
given to those elements that exceed the size or quality anticipated in the budget. Scope,
schedule and budget assumptions are tested after each phase of the design.
During the pre-construction phase contracting strategies
will be developed and general contractor prequalification will take place. Orders may be
placed for long lead equipment and/or materials during this phase.
Specific tasks during pre-construction include:
A. Develop Master Project Schedule
Intelisyn, Inc. uses Primavera Project Planner
to develop detailed CPM schedules for each project. The schedule includes logically
sequenced construction activities, all milestones for the completion of design, the
jurisdictional approval process and close-out requirements. The master schedule may
include activities for owner contracted vendors. The critical path allows fast track
options to be developed and the identification of long lead items. Early detection of
critical items and implementation of effective control systems, will mitigate schedule
impacts. The schedule clearly identifies the team members responsible for each task and is
updated regularly. All updates are sent to each team member in a format that clearly
communicates their action items and the required completion date.
B. Develop Project Budget
Intelisyn, Inc. has developed a detailed project
budget format that includes the entire project cost, not only the construction cost. This
is significant since the construction cost is usually less than seventy percent of the
project cost. In addition to budgeting and tracking the construction cost, Intelisyn
typically budgets and tracks the costs/fees for site acquisition, consultants, agencies,
test and inspections, furniture and equipment, and the costs of telephone/data processing
equipment. Intelisyn budgets and tracks the entire project cost.
C. Develop Cash Flow
Model
The master project schedule is cost loaded which allows
the projects cash flow to be predicted with accuracy. By cost loading the schedule,
Intelisyn is able to generate numerous "what if" scenarios and to evaluate their
impact on cash flow as well as the project completion date.
D. Develop Phasing
Plans for Each Project
Component
Intelisyn works closely with each member of the
project team to define phasing requirements, move-ins, move-outs, shift work, utility
shutdowns, etc.
E. Identify
Critical Path Activities & Monitor
Action Items for Each Consultant
Intelisyn will assist in establishing a
"responsibility matrix" of design consultant/project team roles, along with the
integration of milestone activities into the master schedule. Each team member must adhere
to established schedule milestones and defined responsibilities to ensure the successful
completion of the project.
F. Monitor
& Assist the Owner in Identifying & Acting Upon All
Utility & Jurisdictional Agency Requirements
Intelisyn has successfully interfaced with SCAQMD, FAA,
EPA, WRB, DOT, OSHA, OSHPD, City Building Departments, SHPO and OES/FEMA. The approval
process for each of the applicable entities listed above will be integrated into the
master schedule.
G. Assist
Owner With Review & Evaluation of
Value Engineering Suggestions
Intelisyn has effectively coordinated major
value engineering efforts on several large facilities. With a strong background in cost
management and constructability analysis, Intelisyn is able to actively participate in the
value engineering process as opposed to merely reviewing and acknowledging cost savings
suggestions. On-going budget evaluation and establishment of
alternatives for further examination throughout the project ensures the most value for the
owner.
H. Perform Constructability Reviews
Intelisyn has developed a comprehensive drawing
review checklist. This detailed and methodical review of the bid documents minimizes
questions at bid time and R.F.I.'s and change orders in construction.
I. Provide Construction Cost
Estimates
Over the past eleven years Intelisyn, Inc. has
successfully managed the design and construction of over $1.5 billion in health care and
institutional projects. This portfolio of completed projects has allowed us to establish
an extensive cost database that is utilized in the development of construction cost
estimates. For projects where Intelisyn is not providing the construction estimate, we
will actively review estimates provided by the cost consultant and the general contractor.
Outside estimates are reviewed for scope, representative unit costs, escalation, realistic
general conditions, fee and contingency.
J. Provide
Monthly Status Reports (Applies to all
phases)
Each month Intelisyn will provide a project
status report that summarizes the progress of work in a narrative and photographic format,
and in terms of budget and schedule. This information can be posted on the
Intelisyns website, www.intelisyn.com, where
it can be viewed using a single software application that is provided at no cost. For
security, the document can be protected with a password.
K. Assist in
Coordination & Documentation of
Meetings During the Pre-construction Phase & Track Action Items
Intelisyn actively participates in all
pre-construction meetings and will record and distribute meeting minutes. The minutes
format will document issues, decisions, action items for both individuals and firms, and a
required completion date. Since the team often meets infrequently during the
pre-construction phase, action items are also tracked on a separate list. The list of
action items is updated and issued to all team members weekly. For projects where face to
face meetings are impractical due to the locations of the team members, Intelisyn has full
internet teleconferencing capabilities including collaboration and white board.
Contract Bid/Negotiations Phase
Intelisyn stresses the value of appropriate contract
structure, general conditions and fee negotiation and detailed subcontractor bid review.
Establishing the framework for the GMP/Fixed Price contract and properly structuring the
general conditions allows the owner to realize significant savings immediately and to
benefit from additional minimized costs as the project progresses.
Detailed review of bid tabulation worksheets including
identification of allowances, set asides and line item contingencies for all
subcontractors is essential. Defining the general conditions costs and locking in
subcontractor labor rates for change order work are additional controls utilized by
Intelisyn to ensure more predictable costs during construction.
The foundation for proper team communication and
document flow during construction is established at this stage via the "Construction
Administration Protocol" document.
Specific tasks during contract bid/negotiations may
include the items listed below. The list includes tasks for both GMP and Fixed Price
contracts.
A. Review
Proposed Construction Contract Language,
Requirements, and Make Recommendations
As a result of this review, Intelisyn has
developed major portions of GMP/Fixed Price contract for several large owners.
B. Manage R.F.P.
Process for General Contractor
Selection
Intelisyn will develop a project specific
R.F.P.
for the general contractor that will ensure that the bids are submitted in a form that
allows comparison and evaluation. Any bid alternates will be broken out. The
R.F.P. will
include all unique owner requirements such as union labor, prevailing wage, MWBE
participation etc. The analysis of the bid results will be presented to the owner with
Intelisyns recommendation.
C. Review
Proposed General Conditions in Detail & Advise the Owner on Industry Norms and
Options for Cost Savings
Intelisyn has developed a historical database of
general conditions costs and staffing requirements for various size projects which enables
Intelisyn to negotiate general conditions costs to reasonable amounts. There are several
ways for the owner to reduce the general conditions costs on the project. For example, if
a project is longer than a year, savings can be realized by furnishing the contractor with
office equipment that will be returned to the owner at the end of the project. This means
that the contractor will not have to incur rental costs each month and, at the end of
project, the owner will have additional office equipment that was paid for by the
construction project.
D. Assist in Fee Negotiation
Intelisyn has consistently negotiated the
general contractor's fee to a percentage that is commensurate with the project scope and
current market conditions.
E. Review the
Subcontractor Bid List & Assist
in Prequalifications
The general contractors bid list is compared to
a database of pre-qualified subcontractors. In addition to assuring that the
subcontractors on the list are financially stable and have acceptable levels of
workmanship, the list also allows Intelisyn to confirm that subcontractors who have
provided the lowest bids on similar projects are included on the bid list for the project.
There is an opportunity for significant savings by making certain that the subcontractors
who typically provide the best pricing are included on the bid list. The database will
also note the subcontractors with MWBE status.
F. Review
Subcontractor Bids & Assist Owner
in Evaluation of Subcontractors Proposed by the General Contractor
The general contractor's bid tabulation worksheets are
reviewed for completeness, unit pricing, exceptions, qualifications, acknowledgement of
addenda, labor rates for change order work and any other special conditions.
G. Provide
Construction Contract in Final Form
With Any Other Required Documentation
Intelisyn will provide the construction contract
as either a final draft or the final document as determined by the owners
procedures. The contract can be provided in electronic format using either Microsoft Word
or Corel Word Perfect. Intelisyn will assist with the completion of any internal documents
that must be provided as part of the contract approval process. Intelisyn has experience
in preparing board motions for contractor approval on public projects.
H. Develop a
Project Specific Construction
Administration Protocol
During the construction process there are
hundreds or thousands of documents generated. The list of different kinds of documents
includes requests for information, submittals, instruction bulletins, change order
requests, change orders, allowance allocation requests, applications for payment, meeting
minutes, inspection reports, schedule updates, warranties, operation and maintenance
manuals and punch lists. To ensure a successful project, each document must contain certain
necessary information, and must be routed to the proper individuals who will take the
required actions. After the required actions are taken, the documents must then be
properly routed back to the originator with copies to other applicable parties. The
requirements for processing each of the documents listed above are different. Intelisyn
will develop a project specific Construction Administration Protocol that describes the
procedures for processing each of the documents listed above. This protocol is
incorporated into the contract.
Construction Phase
During the construction phase Intelisyn monitors the
projects scope, schedule, and budget. The flow of project documentation is managed
in accordance with the Construction Administration Protocol. Intelisyn will review and
advise the owner on extra cost issues, pay applications, and the delivery/installation of
OFOI and OFCI equipment is coordinated. Reports from the Inspector of Record, Deputy
Inspector and field observation reports from the consultants are reviewed and the
correction of any deficiencies is tracked. Project status reports will be provided to the
owner monthly using the format established during the pre-construction phase.
Specific tasks during the construction phase include:
A. Attend
Preconstruction Job Walk with General
Contractor, Architect, and Owner
Intelisyn actively participates in the
pre-construction job walk to identify existing conditions, lay down, staging and storage
areas, crane location, routes of ingress and egress, vehicular flow, equipment/material
delivery locations, contractor parking areas, site safety and security measures,
pedestrian protection etc.
B. Maintain Accounting of Project
Budget
The project budget is updated as actual costs
are known and commitments are made. The allocation and disbursement of contingencies and
allowances is tracked. A summary budget report is included in the monthly status report.
C. Maintain & Update
Project Master Schedule
The master schedule is updated to reflect actual
progress and any potential changes in logic.
D. Assist
Owner in Coordination of Owner Provided
Vendors, Subcontractors & Equipment
Intelisyn will interface with owner contracted
vendors including security, radiology, communication systems, fire alarm and any other
OFOI or OFCI equipment. Delivery and installation will be shown on the master schedule.
Intelisyn will direct pre-installation meetings and confirm that the general contractor
has made all contractually required provisions for the installation of equipment.
E. Direct
Weekly Construction Meetings
Intelisyn directs all weekly construction meetings and
will participate as required in any special meetings to review outstanding issues or to
address specific concerns. Intelisyn will prepare meeting minutes in a format that
documents issues and decisions made. The minutes will state what actions are required,
which organization is responsible for the specific action item, and identify a required
completion date. The minutes are issued via E-mail within two business days to remind all
team members of their commitments.
F. Assist the
Owner in Evaluation & Negotiation
of Change Orders
All change order requests from the general
contractor are thoroughly scrutinized. The change order request is first reviewed for
entitlement and then for cost. Labor rates are compared to Intelisyns database of
local union and prevailing wages. Material costs and production rates are verified against
our database and industry standards. Material quantities are verified. Change order
requests are also compared to the engineers estimate. Discrepancies are investigated and
reconciled. This review and verification process insures that the owner is paying a
reasonable price for the work in the change order.
G. Assist the
Owner in Reviewing & Enforcing
Procedures for General Contractor Pay Requests
Intelisyn ensures that the General Contractor
submits documented back up for all monthly general conditions costs. A comprehensive
review of all billed costs including verifying the subcontractor progress payment vs. work
in place is thoroughly scrutinized. Intelisyn also establishes milestone job site visits
for critical pay periods from the mechanical, electrical and plumbing design consultants
to further validate the progress payment. Intelisyn, Inc. will inspect all materials
stored offsite that are included in the pay request. Each subcontractor is required to
submit a conditional release for the current month and an unconditional release for the
prior month. This process insures that the owner only pays for work completed and is
protected against unnecessary liens.
H. Assist the
Owner in Enforcing All General
Conditions of the Contract
Intelisyn will have an in depth knowledge of the
general conditions to ensure that the owner's interest will be protected and will provide
recommendations on all contractual issues.
I. Oversight of the R.F.I. Process
The status of R.F.I.s will be reviewed at
each meeting to ensure timely responses. Responses will be reviewed to make sure that they
do not add cost where additional cost is avoidable.
J. Oversight of the Submittal
Process
The status of submittals will be reviewed at
each meeting. Intelisyn ensures that critical path submittals are submitted by the
contractor in a timely manner and that the architect responds within the established turn
around time. The owner's copy of all submittals including shop drawings, product data and
samples are maintained at the job site, sorted, categorized and turned over to the owner
at project completion.
K. Review
Construction CPM Schedule
The initial construction schedule provided by the
general contractor and the monthly updates are reviewed for reasonableness and contract
adherence. Intelisyn confirms that all project components are shown and that there is a
reasonable amount of float time. This minimizes requests for time extensions and the
resulting added costs.
L. Coordinate Test and
Inspection Services
Intelisyn works closely with governing agencies,
the engineer and the owner to identify the requirements for deputy inspection. The
requirements will be incorporated into an R.F.P. for deputy inspection services. In
addition to coordinating test and inspection services, Intelisyn can perform quality
surveillance as necessary.
M. Verify witness of
All On & Off-Site Testing
Intelisyn will observe and represent the owner
for all on and off site testing such as curtain wall or exterior skin stress testing,
testing of pumps, centrifuges or other equipment. Intelisyn maintains a complete file of
all tests and inspection reports throughout the project duration.
N. Monitor
& Enforce As-Built Drawing Up-Dates
by Contractor
Intelisyn will ensure that all as-built drawings
are updated monthly prior to disbursement of the progress billing.
O. Monitor
& Coordinate Phased Turnover of
Systems
Intelisyn can develop individual work plans for phased
completion and turn-over of subsystems. This is done in close coordination with the
engineer.
Project Close-Out Phase
Intelisyn understands the necessity to properly close
out the construction project. All documentation including final billing, retention
releases, unconditional lien releases, completed punch list, completed as-built drawings
and transfer of operation and maintenance manuals is verified. Copies of all submittals,
shop drawings, product data and samples are transferred to the owner at project
completion.
A. Monitor
& Verify Equipment Start-up & Testing
Intelisyn assists the owner in scheduling the
review and turn over of all systems. Witnessing of equipment start up and testing will be
coordinated with plant operations personnel along with training.
B. Monitor
Turnover of All Operation & Maintenance Information
Intelisyn will ensure a comprehensive turnover
of all operation and maintenance manuals, guarantees, warranties, certificates and
instructions prior to the owner taking beneficial occupancy of the system.
C. Oversee Completion of
As-Built Documents
Intelisyn will ensure the turnover of all
as-built documents to the architect and monitors the transfer of the contractors mark-ups
into the CAD drawings. Intelisyn will confirm that all bulletins and R.F.I.s are
included.
D. Coordinate Owner
Responsibilities for State
Agency Approvals
Intelisyn will monitor and assist the Owner in
securing all appropriate state agency approvals within the established construction
schedule.
E. Provide
Final Accounting & Facilitate Final
Application for Payment
Intelisyn will ensure that all punch list items
are complete including the obtaining of certificate of occupancy prior to processing the
final certificate of payment.
Post Occupancy Evaluation
The success of the teams relationship should be
reflected in the satisfaction of the owner's team and user group, the amount of money
saved, the time, frustration and stress relieved off the owner's project manager and the
insightful professional expertise contributed during the course of the project.
The intent is not only to provide the Owner with a
project that is completed on time and under budget, but also to find ways to improve the
process for the next project.
Assist Owner in Planning & Implementation of Post
Occupancy Evaluation Process
The evaluation will include all facets of the
process and shall be used to evaluate the performance of all team members and consultants.
The evaluation will include the documented fee/savings ratio by the construction manager.
There is always opportunity for improvement in the planning, pre-construction and
construction phases of each project. The post occupancy evaluation is a formalized method
of applying lessons learned to future phases and/or future projects.